Facebook

PROJECT DETAILS

We had to ensure that an endangered species of plant was not disturbed or destroyed by any of our subcontractors actions. A part of the Facebook data center went online and was live before we were halfway complete with the project.

We finished the other half of the project without disturbing the operations in progress.  A full time Safety Rep and Quality control rep was required onsite.  We finished the project on schedule with the client’s goal of Zero Defects.  Subsequently, we were awarded the 2nd phase of construction.

PROJECT DETAILS

Operating Unit: Tecta America Carolinas
Client: Facebook
Industry Type: Data Center
Project Type: New Construction, LEED
Location: Forest City, NC
Square Footage: 24,962
Systems Installed: Modified Bitumen, Low Slope