Roofing replacements on a three-building campus in the Denver Tech Center. Remove rock ballast and existing roofing system down to the concrete decks. Install new roofing insulation and a fully adhered EPDM roof on each building. Unique challenges – rock removal was manually done with crane and Tecta field crews on weekends to minimize customer and tenant disruptions; trash removal was done via crane on weekends; LVOC adhesives and peel and stick membranes were utilized to mitigate fumes and complaints. Custom patio paver installation using “Firestone Sky Pavers” and drainage on 1-building
PROJECT DETAILS
Operating Unit: | Tecta America Colorado |
---|---|
Client: | SteelWave LLC |
Industry Type: | Education |
Project Type: | Roof replacement |
Location: | Greenwood Village, CO |
Square Footage: | 70,000 |
Systems Installed: | Firestone Fully Adhered 60-mil EPDM, Sheet Metal Flashing & Trim, New Paver Deck system |